Consent Preferences
top of page
Construction site

Nebraska Construction Lien Guide

Nebraska Construction Lien Guide

Nebraska mechanics lien law is governed by Nebraska Revised Statutes §§ 52-125.


If you provide labor, materials, equipment, or professional services that improve real property in Nebraska and are not paid, lien rights are available. 


Nebraska applies different notice requirements depending on whether the project is residential and whether the claimant has a direct contract with the property owner.


Keep in mind that Nebraska Mechanics Lien, Construction Lien, and Claim of Lien are commonly used interchangeably to describe the same statutory lien right.

LET’S LEARN THE BASICS OF NEBRASKA CONSTRUCTION LIENS

⭐ Who Can File a Mechanics Lien in Nebraska?


Nebraska grants mechanics lien rights to the following parties who improve private real property:

  • General contractors

  • Subcontractors

  • Sub-subcontractors

  • Material suppliers

  • Laborers

  • Certain design professionals (when services relate to property improvement)

🚫 Mechanics liens do not apply to public projects, which are protected through payment bond statutes.

⭐ Nebraska Lien Deadlines (Critical)


⭐ Nebraska Preliminary Notice Requirements


Nebraska does not require a preliminary notice before filing a mechanics lien on most projects. However, Nebraska does require notice to owner in residential construction.


Deadline #1 — Nebraska Residential Notice Requirement


For residential projects involving one- to four-family dwellings, subcontractors and suppliers who do not have a direct contract with the owner must provide written notice.


Who Must Send the Nebraska Notice:

  • Subcontractors

  • Sub-subcontractors

  • Material suppliers

  • Any party without a direct contract with the homeowner

Who Does NOT Need to Send the Nebraska Notice

  • General contractors contracting directly with the owner

Nebraska Notice Deadline


The Nebraska Notice to Owner must be delivered within 45 days of first furnishing labor or materials

Failure to provide this notice on qualifying residential projects can void lien rights entirely.


Deadline #2 — File the Nebraska Mechanics Lien


A Nebraska mechanics lien must be recorded within 120 days of the claimant’s last furnishing of labor or materials. The Nebraska mechanics lien will need to be filed with the Register of Deeds in the county where the property is located.


This deadline applies to all lien claimants.


Ensure that the Nebraska mechanics lien includes the following:

  • Claimant’s legal name and address

  • Property owner’s name

  • Name of the party who hired the claimant

  • Legal description of the property

  • Description of labor or materials furnished

  • Amount claimed as unpaid

  • Dates of first and last furnishing

  • Verification or sworn statement


Deadline #2 — Serve the Nebraska Filed Lien (Mandatory)


After recording the Nebraska mechanics lien, the claimant must serve a copy of the lien on the property owner within 10 days after recording the lien.


Accepted Methods of Service

  • Certified mail, return receipt requested

  • Personal service by sheriff or other authorized officer

Failure to timely serve the lien invalidates the lien, even if it was properly recorded.


Deadline #3 — Enforce the Nebraska Mechanics Lien


To preserve Nebraska lien rights, the claimant must file a foreclosure lawsuit:

  • Within 2 years after recording the lien

If enforcement is not timely commenced, the lien expires automatically.

bottom of page