Heading 3
1. How long do I have to file a Maine construction lien?
In Maine, a mechanics lien must be recorded within 90 days of the claimant’s last furnishing of labor or materials to the project. The “last furnishing” must reflect actual lienable work, and should not include warranty work, punch-list repairs, inspections, or administrative tasks.
Heading 3
3. Who can file a construction lien in Maine?
Mechanics lien rights in Maine extend to parties who improve private real property, including:
General contractors
Subcontractors
Sub-subcontractors
Material suppliers
Laborers
Certain design professionals when services directly improve the property
Mechanics liens do not apply to public projects, which are protected through bond claims instead.
Heading 3
7. What information must be included in a Maine construction lien form?
A Maine lien claim must include:
The name of the lien claimant
The name of the property owner
A description of the property sufficient for identification
The amount claimed
A statement of the labor or materials provided
The date of last furnishing
Heading 3
8. Is there a dollar limit to filing a Maine construction lien?
No. Maine does not impose a statutory minimum or maximum lien amount. However, the lien must reflect the actual unpaid balance for lienable work. Inflated or unsupported lien amounts can expose the claimant to lien invalidation and potential damages.
Heading 3
10. What should I do after the customer pays a Maine construction lien?
If the customer pays you the full amount owed after you have recorded a lien, you have a legal obligation to formally clear the lien from the property records.
You must prepare and file a Maine Discharge of Lien (or Release of Lien) with the same office where the original lien was recorded.


